The team behind a proposed data centre south of the Keephills Generating Station goes back to the community hall on December 3 with one advantage few Alberta projects can claim: a signed contract for 230 megawatts of grid demand. Parkland County says it has yet to receive a development application for the Boreal Technology Hub. Those two facts tell residents where the proposal stands. The province’s grid operator has allocated some power capacity. The county has not yet been asked to approve a construction plan.
The Boreal project team is hosting the drop-in open house from 3 to 7 p.m. at Keephills Community Hall, 15-51515 Range Road 32A. Parkland County’s notice says the team invited advance questions by November 25. Residents can still attend and ask questions in person. This is a meeting with the proponents, not a hearing before county council.
What the grid contract covers
The Alberta Electric System Operator awarded its entire 1,200 MW interim large-load allocation to two projects. Keephills secured 230 MW, and the other project secured 970 MW. The system operator says both now proceed through its connection process. An executed load contract is a concrete milestone, but the connection process is still ahead and the allocation does not authorize construction.
Boreal’s proponents describe a campus that could eventually reach up to 1,600 MW. That number describes the scale of a possible build-out, not grid capacity already secured. It is roughly seven times the amount in the existing contract. If Boreal seeks additional grid capacity, the system operator says those requests would fall under the next phase of its large-load program. What residents have not yet seen in a filed plan is how much power each stage would actually draw, which upgrades that demand would require and who would pay for them.
The project grew out of a February memorandum of understanding between Brookfield, CPP Investments and TransAlta to evaluate a development at Keephills. The proponents estimate more than $5 billion in first-phase investment and say it would support more than 1,000 construction jobs and 150 operations jobs. Those are forecasts, not contracts for work. For local trades and suppliers, the more useful figures would be the size of the workforce at each stage, how many jobs are expected to last beyond commissioning and what share of contracts local businesses would be in a position to bid on.
The county has opened a route to apply
Parkland County council amended its land-use bylaw and the Highvale End Land Use Area Structure Plan in September 2025. The county says those amendments allow data processing facilities to be considered near the Keephills and Sundance generating stations. They did not approve a building on either site.
The county expects BGRE to submit the development application on behalf of Brookfield and CPP Investments in the coming months. Its project notice says a master site development plan and a development permit would be required before construction. The plan is where the county would consider effects that reach beyond an individual building, including traffic, drainage and environmental impacts. Council would decide on the master plan and data centre building permits through a public hearing process; county staff would decide on permits for supporting structures.
The province is separately proposing Bill 42’s large data centre rules, including a larger role for the Alberta Utilities Commission and limits on how close large projects can be to homes. That proposal should not be mistaken for a Keephills decision. Once a development plan is filed, the county and province can explain which rules would apply to the actual buildings and whether earlier land-use decisions affect that review.
The water estimate uses a different power figure
Boreal’s October open house boards describe a closed-loop system designed to recirculate cooling water. The project team expects to use existing TransAlta water infrastructure and cooling ponds and says it would not withdraw from Wabamun Lake. Its preliminary example puts an initial fill at about 7,952 cubic metres and annual make-up water at about 700 cubic metres. The two figures measure different things: the initial water required to fill the system and the water added later for leaks, maintenance and chiller requirements.
The boards use a 300 MW facility as their planning example. That is not the 230 MW grid contract, and those figures do not describe a full 1,600 MW campus. The filed plan could make the comparison useful by showing which buildings the estimate covers, whether it includes all site uses, and what the annual and seasonal demand could be if more phases proceed. Some residents will also want to know who would report measured water use once the facility is operating and whether those figures would be public.
Noise raises a similar issue. The October boards outline a study of existing sound, equipment, local weather and combined effects at nearby homes. At the open house, residents can ask to see which homes were used in the assessment and what the model assumes about night operations and backup equipment running at the same time. The nearby generating station makes it particularly important to identify which existing sources the assessment includes before drawing conclusions from any single noise figure.
The record after the open house
For more on what the province’s grid operator expects to recover from customers, see NorthwardAB’s coverage of Alberta’s proposed transmission rates.
Parkland County requires the applicant to file a report on what it heard during public engagement. That creates a way to compare the December discussion with the plan the applicant eventually files. A useful report would show what changed in response to concerns, which questions remain unresolved and what evidence will be available for council’s hearing. For now, the most important milestone is still the application itself: it would put the proposed buildings, their operating assumptions and their effects on the public record in a form the county can assess.
Reporting sources
- Parkland County: Boreal Technology Hub application and public engagement
- Boreal Technology Hub: project details and December 3 open house
- Alberta Electric System Operator: large-load allocations
- Boreal Technology Hub: open house boards and technical materials
- Government of Alberta: proposed data centre rules