A week after TC Energy proposed a 370-kilometre gas line to Alberta’s oilsands, the province introduced a bill that would let it build gas infrastructure that the energy minister believes otherwise won’t be built. The two proposals point to the same problem: adding gas supply in Western Canada doesn’t help a plant or an oilsands operator if there is no space to move it where they need it.
Energy and Minerals Minister Brian Jean’s Natural Gas Infrastructure Act passed first reading Monday. Bill 45 doesn’t approve a route or fund a project. It would create a way for Alberta to decide where the gas network should grow and give cabinet options if the companies that normally build it don’t follow.
The construction power in section 13 has two conditions. The infrastructure would first have to be identified in a plan as something that may need to be built. Then the minister would have to conclude it wouldn’t otherwise be built, and cabinet would have to approve the province’s involvement. In a separate part of the same section, the bill would let cabinet approve government loans, guarantees, grants or joint ventures. That could put public money at risk even if a private company builds and runs the project.
Cabinet could decide which lines are critical
The bill also gives cabinet power to designate critical gas transmission lines. In those cases, cabinet could have the Alberta Utilities Commission require an owner to apply for a pipeline licence. The commission could order construction and operation if it grants the licence. The designation would settle the question of future need for the commission, but someone would still have to submit a project for licensing.
Bill 45 leaves room for separate organizations to do the planning and the building. Cabinet could create corporations for those jobs, or the minister could perform the planning function while no authority is designated. The planner could undertake public consultation; the minister could order it. Neither the composition of a new body nor the terms of consultation are settled at first reading.
What a proposed line to the oilsands would test
TC Energy has already set out what it thinks buyers will need. Its November forecast puts demand on the NGTL system at about 18 billion cubic feet a day in 2031, up from 14.4 billion in 2026. It expects oilsands, power generation and data centres together to account for more than 60 per cent of that increase. The company does not assign that entire share to AI campuses.
The proposed Alberta Growth Connector would start with about one billion cubic feet a day of capacity. TC Energy says it could offer customers more chances to contract for new service as early as January 2027. That would test what customers will pay to reserve. In announcing the proposal, chief executive François Poirier said TC Energy would “align investment with customer commitments.” The pipeline still needs commercial support, engagement with Indigenous rightsholders and other stakeholders, regulatory approvals and a corporate investment decision.
Chief executive François Poirier warned in a Nov. 21 letter to Premier Danielle Smith, reported by The Narwhal, that the proposed policy could make it harder for the company to advance its expansion plans. The private-sector proposal remains on the table. NGTL is an interprovincial network regulated by the Canada Energy Regulator; first reading of a provincial bill does not transfer that oversight.
January is the earliest TC Energy says it could ask customers to book more space. If major users reserve space, those commitments help a company decide how much it can afford to build. If the province still sees a gap, Bill 45 offers it a way to take on some of the risk. It leaves the cost, the terms and the specific line for another decision.