Long before a carbon capture plant can put a tonne of carbon dioxide underground, someone has to pay for the equipment that separates it, the compressors that prepare it for transport and the connections that carry it to a place where it can be stored. Alberta says it will now let eligible projects receive some of their provincial grant while that work is still under construction, instead of waiting until the project is complete and operating.
The province announced the change Nov. 19 and said it would extend funding through 2035. The grant rate remains 12 per cent of eligible capital costs. That is not 12 per cent of every dollar a company spends on a project. Alberta has not said in the announcement how much of a grant could be paid during construction, what milestones would trigger a payment or what would happen to money already paid if a project stalled.
Earlier payments could reduce how much private capital a company needs to carry until a project opens. They can also move some public spending ahead of the point when the equipment is capturing and storing carbon dioxide. How much that matters depends on the payment terms. A reimbursement after a piece of equipment is installed is different from a payment that arrives before the bills are due, and the announcement does not say which construction costs could be reimbursed first.
The published program terms describe an annual payment process after verification of eligible costs incurred the previous year. They also set out a separate qualification step before Alberta enters a grant agreement with an eligible applicant. Projects must be in Alberta. Approved capture, compression, transport, storage or other qualifying equipment can count, but engineering studies, pilots and proof-of-concept projects do not. The program page says detailed payment and reporting specifications are to come in formal guidelines. Until those terms are available, the construction announcement is a change in the proposed timing of payments, not a schedule a prospective recipient can use to calculate its first cheque.
A funding change, not a construction decision
The province singled out Pathways as one of the projects it hopes to advance. The Oil Sands Alliance proposes a main carbon dioxide pipeline between the Fort McMurray and Cold Lake regions, with connecting lines from oil sands facilities bringing the total network to more than 650 kilometres. Captured gas would be carried to an underground storage hub in the Cold Lake area. The network remains proposed. A program extension can help the companies plan, but it is not a grant award to the Alliance or permission to build the network.
In July, Canada, Alberta and the Alliance companies reached a memorandum of understanding that contemplated binding agreements with each participating company. It set Nov. 15 as a target for signing. The target has passed, but the public government and Alliance records reviewed for this article did not confirm that those agreements were signed. The Nov. 19 announcement did not name a grant recipient or announce a final investment decision for Pathways. Those are separate milestones from the provincial program change.
The regulatory files tell a separate story. The federal registry still lists as suspended a request to designate the project for a federal impact assessment. That is a pause in the process for deciding whether to designate it, not a decision to reject the project or a suspension of an assessment already underway. In a September letter to the agency, the proponent said an outstanding provincial carbon sequestration agreement was a main reason it had requested the pause. A sequestration agreement concerns rights to use underground storage; it is not the capital grant Alberta announced this week. Provincial regulatory approvals are also a separate requirement.
There is a nearer date for residents following the proposal. After listing a Nov. 18 session in Fort McMurray, the Alliance is advertising open houses at the All Saints Ukrainian Cultural Centre in St. Paul on Nov. 24 and at the Lakeland Inn in Cold Lake on Dec. 2. Both are scheduled from 4 to 7 p.m., with a presentation at 5:30 p.m. The meetings are opportunities to ask what is known about the route and storage area. The question for Alberta is different: when will it release the conditions that determine how much public money can go out before a project starts capturing carbon?