Sturgeon Lake Cree Nation asked Ottawa in June to require an impact assessment of the gas-powered AI campus proposed south of Grande Prairie. The minister's reply, included in the Nation's federal filing, said the developer had not yet submitted an initial project description. By the time the Nation wrote again in October, the federal rule that used to send new fossil-fired plants of a certain size into the assessment process was gone.
The November 17 update to the federal registry is the first public sign on that file of what will happen next. The Impact Assessment Agency of Canada is analyzing the Nation's October 27 request and will make a recommendation to its president. No decision to designate Wonder Valley has been posted, and the government has not ordered a full assessment.
The difference matters. The Nation is not asking Ottawa simply to rule on a gas plant. It is asking it to treat the power supply, data halls and river works as one industrial project, then decide whether that project warrants a full federal assessment. The federal description already groups those components in a four-phase proposal that could include up to 9,000 megawatts of gas generation and eleven 500 MW data centre clusters across about 6,417 hectares. That description is not a ruling on which parts would be assessed. Nor is 9,000 MW a measurement of the data halls' electricity use.
What changed in September
Until September 3, the federal project list captured new fossil-fired power generating facilities with production capacity of at least 200 MW. Meeting that threshold brought a project into the process. It did not guarantee a full assessment. A more recent example is the 650 MW gas plant proposed to power the Mihta Askiy data centre northeast of Peace River. Its old-rule planning phase included a January 2 to 22 public comment window. The agency decided in March that a full assessment was not required, pointing to limited effects or the ability of existing federal and provincial laws to address them. That was a screening decision, not a construction permit. At Wonder Valley’s current designation-request stage, there is no formal federal comment period, although the agency can seek input.
The September amendment repealed the gas-plant listing. The federal government said past fossil-fired projects had consistently not required comprehensive assessments, either because of their limited potential for adverse effects within federal jurisdiction or because other federal or provincial rules could address those effects. That is the government's explanation for changing the rule, not a finding about Wonder Valley.
Even without that listing, section 9 of the Impact Assessment Act allows a case-specific designation where a previously unlisted activity may cause the adverse effects described in the law. The statute allows consideration of effects on Indigenous rights and whether another process can address the federal effects. The agency president can make that decision under authority delegated by the minister. If Ottawa designates the project, that would still leave a separate decision on whether to require an impact assessment.
The Nation's October filing argues that treating these facilities separately could miss effects on fish habitat, migratory birds and the exercise of Treaty 8 rights in an already industrialized part of the Smoky River watershed. A March 19 project summary from O’Leary Digital, attached to the filing, shows what power would come on first. It calls for 500 MW of interim gas generation, followed by three 500 MW combined-cycle cogeneration units. The interim turbines would become backup. The developer’s public FAQ describes up to 2 GW of on-site generation for that phase, while Alberta’s project inventory describes a 1.4 GW off-grid system. Those descriptions do not resolve how much generation would run at once, or on what schedule. None is a permit or an operating result.
What the water licence does not answer
The developer says it has access to licensed supply of up to six million cubic metres annually and expects to use less than that even at full buildout. The March project summary, by contrast, lists up to 24 million cubic metres as potential annual intake. Those are statements from different records, not two readings from the river. The Environmental Appeals Board's decision describes a different thing: an interim Water Act licence issued to the Municipal District of Greenview for commercial and industrial use across the industrial gateway. Six million cubic metres is the municipal annual diversion limit, not a forecast of what Wonder Valley will use. The board's decision records that the licence also sets a maximum diversion rate of 0.56 cubic metres per second. The developer’s March summary describes a permanent intake designed to divert up to 1.2 cubic metres per second. The design figure does not authorize that withdrawal.
The board’s record also describes a separate 2024 preliminary certificate for a larger municipal allocation. A preliminary certificate is not authority to take the water. The board dismissed the Nation’s appeal for lack of standing; it did not decide whether the Crown had fulfilled its duty to consult on the project. What remains unclear from the public records is how much river water the first phase plans to take, what it would put back and under what conditions. Those questions concern the intake and treatment works as much as the server halls.
Federal guidance gives Ottawa 90 days to respond once the agency has enough information to start the designation process. The registry shows a November 17 start date but gives no response deadline for this request. The agency can suspend the clock and must post its reasons if it does. The next decision is whether Ottawa will bring the campus into the process at all, and what it counts as part of the campus when it explains why.