At the proposed data centre near Brooks, the gas generators in the first design are rated at 9.6 megawatts. An expansion could take them to 19.2. FingerMotion disclosed that option on November 18, subject to more permits. On the same day, Alberta said it wanted new siting rules for data centres of 10 megawatts or more.

The numbers line up neatly until you ask what they measure. The company’s announcement, filed with the U.S. Securities and Exchange Commission, puts installed generating capacity at 9.6 megawatts and power available for computing equipment at a targeted 7.2. It plans to run the site without relying on the provincial grid. The 19.2 figure describes a possible expansion of generation, not what the data centre would draw at its busiest.

Alberta’s Bill 42 looks at what a data centre consumes. The province’s summary says data centres at or above 10 megawatts would come under the Alberta Utilities Commission as the main provincial regulator, with a proposed 600-metre minimum setback. The bill leaves the threshold amount, setback details and part of the transition for existing projects to regulations. Its definition of a data centre can cover more than one building, but the text does not spell out how the provincial review would account for future phases.

There is already a 10-megawatt line in a different part of Alberta’s rulebook. A new power plant on a site with total generating capability of at least one megawatt but less than 10 can use the AUC’s shorter checklist application. FingerMotion’s September announcement described ten 9.9-megawatt generation and data hall sites, and its September filing says the first Brooks-area site comes with a Rule 007 registration. That is a record about the generating plant. It cannot tell a neighbour whether the data hall will be subject to the proposed setback.

Brooks is meant to be the design the company can reuse across its 99-megawatt program. That total is gross generating capacity across several parts of Alberta, not one centre’s demand. The more immediate question is what happens on a single property. If more generators and server halls are added at Brooks, will the assessment look at the first phase, the combined demand at expansion, or the build-out the developer plans from the start?

For people near a site, the answer matters before anyone measures 600 metres on a map. The most useful thing Alberta could put in the regulations is a clear instruction about which load to count and when to count it. Then a neighbour reading the next project notice would know which number to look for.

Reporting sources