New Brunswick wants a decision on whether a utility should pursue a data centre’s request for electricity before the utility spends time studying a deal. Bill 15, introduced Nov. 20, would require two written approvals: one to begin negotiating or studying an electricity supply contract, and another before the utility can serve the project under that contract.
New Brunswick says distribution utilities currently evaluate connection requests individually in the order they arrive. The proposed change would add a separate decision about whether a project should advance. It is not a provincewide refusal to serve data centres. It would make a developer’s place in the existing process less decisive where the project has yet to turn that work into a binding supply agreement.
Where the two approvals would apply
The bill leaves the identity of the decision-maker at each stage to regulations. It also leaves the definitions of “data centre” and “other business” to regulation, so the text does not identify every customer that would need to apply. Permission to do studies would not bind either side at the contract stage. The completed agreement would still need written approval, and proposed amendments to an approved agreement would have to go back for approval as well.
The distinction matters for proposals already in the queue. Prior negotiations or a completed study would not exempt a proposed deal. A contract entered into by the time the provisions commence would be outside the new two-stage checks for that supply, and an operating customer could carry on under its existing arrangements. The relevant date is commencement, not introduction. The province says the legislation would take effect on proclamation if passed.
There is a limit to that protection. The bill applies the new sections to expansions, increases in required capacity and increases in electric service requirements. It also expressly covers conversion of an existing customer into a data centre or other covered business. A narrow exception would apply to a cryptocurrency mining business with a new Network Operating Agreement with the utility and unchanged electricity service requirements at commencement. Having an existing meter, in other words, would not necessarily allow a business to change what it does or how much power it takes without further review.
What ratepayers would be protected from
For existing utility customers, the important clause is the test at the second approval. The decision-maker must reasonably expect the deal to deliver at least a prescribed monetary benefit to the distribution utility and not increase costs for its existing customers. The business would also pay the direct and attributable costs identified in regulations. The bill does not yet specify which expenses count as direct, what minimum benefit the utility must show or how the costs and revenue should be accounted for.
A new customer can generate revenue and still require spending the utility would not otherwise have incurred. A connection can involve costs specific to that site, while meeting the customer’s electricity needs can affect broader system planning. How those categories are defined is important because the law would treat an approved contract, and the utility’s related costs and revenues, as prudent. The approved customer would also sit outside ordinary rate classes for allocating costs and setting rates.
That does not mean a data centre will be exempt from paying for electricity. The bill would disapply section 104, which generally requires NB Power to charge the rate fixed by the regulator for a service, for supply under the approved agreements. The approved contract would become particularly important to understanding what the customer pays. It is not a commitment that household rates will never rise for other reasons.
NB Power already has a large industrial rate category for qualifying data centres with at least 750 kilowatts of firm load and at least 95 per cent of load for data centre functions, including cooling. Those are existing tariff conditions, not a size threshold written into Bill 15. They are also distinct from Alberta’s Bill 42, which proposes an Alberta Utilities Commission approval route for data centres of 10 megawatts or more. Alberta starts with project regulation; New Brunswick’s new provision would start with decisions on utility supply agreements.
Approval for power is only one decision
The province’s wider data centre policy, announced the day before Bill 15, also calls for community and First Nations engagement, reliable power and environmental safeguards. New Brunswick has proposed a separate municipal role in assessing local fit and negotiating community benefits. Preparing a benefits agreement for a community would not, by itself, secure written approval for electricity. A utility study also would not answer environmental or local land-use questions.
NB Power’s 2026 Integrated Resource Plan runs through possible outcomes over 20 years, rather than treating a single path for electricity demand as certain. Bill 15 would add a separate test for individual projects. As the bill proceeds, the documents to watch are the definitions, the method for calculating the benefit and cost test, and the rules that explain how much of a new supply deal existing customers can see.