Calgary is taking data centres to a public hearing in March, but projects can still come through the city’s existing industrial rules before then. Alberta, meanwhile, wants its utilities commission to become the lead provincial regulator for large facilities. A developer choosing a site now has to contend with two governments writing rules on different clocks.
The province’s Bill 42 proposal, introduced November 18, would cover facilities of 10 megawatts or more under the announced policy. Alberta proposes a minimum of 600 metres from the edge of a project site to the nearest home. At Calgary City Hall, the immediate issue is how to review applications arriving before either government has finished its work.
Calgary is working on its own rules at the same time. The city's land-use review says proposed amendments will go to a public hearing in March 2027. They would define data centres as a distinct use and identify where they are permitted or prohibited. A second report, due by the end of 2027, would examine broader risks and opportunities. The city explicitly says it is investigating how Bill 42 could affect its approval process. A provincial announcement has not resolved that question for it.
Nor does a review mean applications have simply stopped. Calgary says proposals with limited on-site generation may continue through the existing General Industrial - Light category. Larger generating facilities may require redesignation to a Direct Control district. Applications are assessed against the rules in force when a decision is made. That is a more precise description of the current position than a blanket assertion that Calgary has banned new data centres.
The distinction between the government's announcement and the bill itself matters. The draft creates powers to prescribe the demand threshold, setbacks and land categories through regulation; it does not print 600 metres and 10 megawatts into the operative approval provision. It also allows regulations to establish a municipality's right to request a setback exemption or variance. Alberta's policy summary describes municipalities requesting an alternative from the Alberta Utilities Commission where local planning supports it. That is not an unrestricted municipal power to waive the provincial framework.
The AUC would become the main provincial regulator for facilities at or above the announced threshold. Alberta says it would oversee requirements covering siting, noise, lighting, heat recovery, water use and farmland protection. Environment and Protected Areas would retain water-licensing and environmental-approval responsibilities. For a resident, the practical implication is that one project's documents may still be spread across several decision-makers. An answer about zoning is not automatically an answer about water, and a power decision does not settle every question about the building beside it.
The province's November 18 announcement also distinguishes a setback from a land-use prohibition. It proposes excluding large data centres from Class 1 and 2 agricultural land, and Class 3 land in municipalities without those higher classes, as well as irrigated land. Those restrictions are not simply another way of saying that a site must sit 600 metres from a farm. Existing noise requirements would continue alongside the distance rule. A proposal beyond the buffer would still have to address its sound impacts.
Water requires similar care. Alberta proposes a cooling-water standard close to zero, not a promise that an entire campus will need no water. The province's water explanation says the proposed standard would be set beyond what evaporative cooling could meet. Other uses, including those of an associated power plant, would still need an appropriate water licence or municipal supply. A claim about server cooling should therefore be checked against the water budget for the whole development.
That distinction is especially relevant in southern Alberta. The Bow, Oldman and South Saskatchewan sub-basins are closed to most new water licences. Depending on the proposal, a developer may need an approved transfer of an existing licence or municipal service supported by sufficient licensed supply. The province says a municipality must agree before its water system serves a data centre. Low-water cooling may reduce demand; it does not itself secure the remaining supply.
Electricity policy has two separate tests: who pays, and whether the system can accommodate the load. The government's Bill 42 overview says proponents would pay for wires within their project footprint and describes a new Data Centre Designation intended to protect other ratepayers. That commitment should be read at its stated scope. It is not a forecast of every household's future bill, nor proof that a particular project's complete connection and operating arrangements have been settled.
The Alberta Electric System Operator maintains a separate connection process. It says all 1,200 megawatts in its first interim allocation went to two projects, which then proceeded through that process. Its next phase examines longer-term arrangements across connections, planning, operations, markets, tariffs and reliability. The operator has also issued technical guidance for transmission-connected data centres. A land-use approval and an available electrical connection are different milestones. Neither should be treated as a substitute for the other.
Existing projects introduce another complication. The draft provides for an exemption tied to a construction or operating stage that would be prescribed later, and a separate provision deems existing constructors or operators to hold an AUC approval while leaving other applicable obligations in place. It is therefore too broad to say that every announced project is grandfathered, or that every earlier permit is cancelled. The transition rules and the project's actual stage will matter.
A developer that applies now will be working with the rules in force when Calgary makes its decision. A neighbour trying to follow the project will need to look beyond the city’s land-use file, to the electricity connection, the water source and eventually the province’s transition rules. The March hearing can tell Calgarians where the city wants these facilities to go. It cannot, on its own, tell them which applications will be decided under the new provincial system.