Anthropic priced its initial public offering at US$83 per share on November 18, above the US$70 to US$78 range it gave investors when it began its roadshow. Nasdaq confirmed the Claude maker began trading on November 19 under the ticker ANT, with a first trade of US$111.50, about 34 per cent above the offer price. The two prices measure different things: what investors paid in the offering and what buyers paid when trading began.

Anthropic confirmed the offering closed on November 20. The underwriters used their full option for 147 million additional shares, bringing the sale to 1.127 billion shares and about US$93.5 billion in gross public proceeds. Anthropic accounted for roughly US$91.6 billion of that total before discounts and expenses; existing holders sold the rest.

Anthropic also closed a separate US$26 billion private placement the same day. The final prospectus said Google and NVIDIA each agreed to buy about US$10 billion of Class N shares. The two deals therefore tell different stories: one prices shares for the public market; the other shows how closely the AI lab’s financing is tied to some of the companies that supply the wider AI industry.

What it costs to run Claude

In the nine months ended September 30, Anthropic reported US$18.8 billion in compute and infrastructure expenses, up from US$4.4 billion in the same period of 2025. Those costs fell as a share of revenue, from 172 per cent to 57 per cent. The two figures matter together. Anthropic brought in far more revenue for each dollar spent on those lines, but the cash and capacity needed to compete are still growing.

The filing also describes a shift from paying cloud providers as computing capacity becomes available toward more leases, equipment and other commitments that may require payment well before a system is operational. For companies buying AI services, that makes future filings worth reading for more than headline revenue. Are customers using enough of the new capacity to justify the commitments, and how much does the company have to pay before it can put that capacity to work? The IPO price cannot answer either question.

Reporting sources