Calgary and neighbouring communities used 480 million litres of water on Thursday, 20 million litres below the city’s daily threshold while crews connect the replacement Bearspaw South Feeder Main. The city published the figure Friday and asked residents to keep conserving water over the weekend. Stage 4 outdoor restrictions remain in place.

The 500-million-litre mark tells the city whether its system can keep up during the shutdown. It does not tell residents whether the new main is ready. Calgary shut down the existing feeder main for connection work on Nov. 4 and expects that phase to last about four weeks. While the pipe is out of service, one treatment plant is doing most of the work and is operating at maximum capacity, according to the city.

That leaves less room to handle a spike in demand. The city says crossing the threshold increases the risk of low water pressure, a boil-water advisory and insufficient water for firefighting. Friday’s update did not announce any of those outcomes. Using less water indoors is a request; the Stage 4 limits restrict outdoor use of treated water, with exceptions listed by the city.

On Thursday, the city said crews were around halfway through the connection window. At the Shaganappi Pump Station near Edworthy Park, workers had finished welding the pipe segments installed so far, with the connection still under way. At 33 Avenue and 89 Street N.W., they were installing the final segments between the new main and the steel pipe leading to the Bearspaw Water Treatment Plant. At 33 Avenue and 83 Street N.W., crews were still digging to expose the existing pipes and had moved to round-the-clock work.

The shutdown also gives crews a chance to repair parts of the existing system that are not being replaced. Along Parkdale Boulevard between Shaganappi and the Memorial Pump Station, the city said Thursday that one replacement pipe segment was fully installed and that work continued on four others. Calgary did not expect the snow or colder weather to change its schedule at the time of that update.

Connecting the replacement main and putting it into regular service are separate operations. The city expects to commission the line in December. The commissioning process includes disinfecting and filling the new pipe. Calgary says it will still rely on the original main during commissioning, so the risk of a break remains even after the connection crews finish.

The city does not expect to need water restrictions during commissioning. For now, Calgary’s restrictions page lists the Stage 4 rules and exceptions. A further day below 500 million litres would give the system more breathing room, but it takes a city notice to change what residents can do.