A Loblaw truck carrying commercial freight arrived at the company’s site in Balzac, north of Calgary, on Nov. 18 after two days and 1,046 kilometres on the road from Vancouver. It ran on hydrogen. To make the delivery, the organizers went beyond checking what the truck could carry or how it would handle the mountain grades. They arranged for fuel to be brought to two stops in British Columbia.
The Edmonton Region Hydrogen Hub announced the run Nov. 19. Loblaw operated a Hyundai XCIENT fuel-cell electric truck leased through HTEC. It fuelled first at HTEC’s Vancouver station, then used mobile refuelling at arranged sites in Sicamous and Golden. The route took it up the Coquihalla Highway and through Rogers Pass and Kicking Horse Canyon before the delivery in Alberta.
The work behind two fuel stops
Powertech used a tube trailer to supply hydrogen at both stops. A tube trailer stores compressed gas in cylinders so it can be moved by road. The trailer used for the demonstration could hold 1,050 kilograms at 517 bar, the Hub said. That figure describes the trailer’s capacity, not how much the truck took on or used. The Hub said the demonstration fuel was made by electrolysis using electricity from the B.C. grid.
Backwoods Energy Services, which is owned by Alexis Nakota Sioux Nation, worked with BDS Inc. on trailer transportation and logistics. Twin Anchors Marine Industrial and HR Pacific Construction Management provided the fuel sites. The Alberta Motor Transport Association supported route planning and vehicle permitting. The arrangement put fuel where the truck needed it without a permanent station at either of those stops, but it still needed a fuel supplier, road transport and places to dispense it.
A 2025 Loblaw and FortisBC demonstration put a hydrogen truck on repeated trips between the Lower Mainland and Squamish, with fuel from HTEC’s Vancouver station. The mountain run asked a different question: how to arrange fuel farther from the truck’s starting point.
For a fleet, the question is whether that setup can work on a standing schedule, not just for a single truck on an arranged trip. A late trailer or a fuel site that cannot serve the next truck on time could disrupt deliveries. A fixed station removes the need to set up the dispensing point for each trip, but the operator still needs a reliable supply and enough customers to keep the equipment in use. The Hub’s announcement does not give the amount dispensed, the delivered cost of the fuel or a comparable diesel run. It cannot settle the cost of repeating the delivery or its emissions across the entire fuel supply chain.
Alberta’s station plans are not all at the same stage
In the County of Newell, Emissions Reduction Alberta lists the Brooks Newell Hydrogen Hub as active. The agency lists $5 million in funding for a $13.3-million project that combines hydrogen production and refuelling with retrofits to trucks and other equipment. The vehicle work is meant to build local demand alongside the infrastructure. The equipment includes dual-fuel conversions, a different approach from Loblaw’s fuel-cell truck. An active funding-project listing does not show that a station is open.
An earlier proposal from HTEC would have put a permanent heavy-duty refuelling station on Highway 2 at Crossfield. Emissions Reduction Alberta announced $2.06 million in funding in March 2024 for the $8.25-million proposal. Its current project record marks it cancelled, without saying when or why. Neither Crossfield nor Brooks was a fuel stop on the Loblaw run.
The Hub says it will use what the partners learned about moving fuel, securing sites and operating the truck in its Western Canada Hydrogen Corridors planning. The Balzac delivery shows that a particular trip can be arranged with a trailer and willing site hosts. The next test is whether fleets can get the fuel they need when another truck has to make the same run tomorrow.