Alberta's utilities regulator has approved a 650-megawatt gas plant for a proposed data centre northeast of Peace River. But it rejected the developer's request to treat the plant and the data centre as a single industrial system for electricity purposes, leaving the company responsible for showing how it can supply the site under Alberta's ordinary power rules.
The November 20 decision is the Alberta Utilities Commission's first ruling on such a designation for a data centre with its own generation. It approves Cree Ative Datacenter Corp.'s plant and the associated Sunrise Substation, subject to conditions. The project's first phase, however, would draw as much as 200 MW from the provincial grid before its gas turbines are ready. The transmission lines it needs to connect to that grid are a separate matter.
A permit to build is not an exemption
Alberta generally requires electricity entering or leaving the interconnected grid to go through the power pool, and customers ordinarily arrange distribution service through the local distributor. An industrial system designation can exempt electricity produced and consumed inside an integrated operation. Cree Ative argued that natural gas and electricity produced on site were inputs and that processing or storing data was the product.
The commission did not accept that argument. In this case, it did not consider electricity alone a feedstock or computing capacity a tangible product for purposes of the designation. It also found the link between the two operations ran in one direction: the plant would supply electricity to the data centre, but the data centre would not send back a useful input or make direct use of the plant's recovered heat. That heat would increase the efficiency of power generation rather than serve the computing operation. The regulator contrasted that design with industrial plants in which the generator and the factory use one another's energy or byproducts.
The denial does not rule out on-site generation for the data centre. One separate provision of the Electric Utilities Act can exempt electricity an owner or tenant generates and uses on the same property, subject to applicable tariff provisions. A 2022 amendment made clear under that provision that part of the power can be used on site even if another portion is exported to the grid. The commission did not determine whether Cree Ative qualifies. The company said it would operate the plant, power infrastructure and data centre itself, but may later host facilities owned or leased by other companies. It must stay compliant if the ownership or leasing arrangements change.
From grid power to two stages of gas generation
The company proposes three phases. The first would bring up to 200 MW of data centre load onto the grid via the Sunrise Substation. The second would add two 200 MW gas turbines and a further 200 MW of data centre load. The third would add 250 MW of generating capacity through a combined-cycle conversion and another 200 MW of data centre load. That is up to 600 MW of proposed load at full buildout, separate from the plant's approved 650 MW generating capacity.
The application cited February 2027 for first service. That is a developer target, not a guarantee. The substation permit gives the initial grid phase until April 15, 2028 unless the commission authorizes otherwise. ATCO Electric is expected to apply separately to connect the site to its Wesley Creek Substation using two new 240-kilovolt lines. The power plant approval sets construction completion deadlines of January 15, 2029 for the simple-cycle equipment and September 30, 2031 for the combined-cycle conversion, unless the commission authorizes a change.
The site comprises about 20.6 hectares of previously cleared Crown land in Northern Sunrise County. An earlier thermal plant there was partially built but never operated. Cree Ative, the general partner for Mihta Askiy Datacenter LP, must obtain provincial consent to transfer the Crown lease before building the plant. The project's federal filing describes the partnership as 51 per cent owned by Woodland Cree First Nation and 49 per cent by Sovereign Digital Infrastructure. In March, the Impact Assessment Agency of Canada concluded that the project did not require a further federal impact assessment. That decision was separate from Friday's plant approval.
The company expects the gas plant to need 5,000 cubic metres of water per day, mainly for evaporative cooling once it uses a steam turbine. It proposes to draw on existing licensed Peace River allocations rather than build a new river intake. The regulator said using a previously unused allocation could still affect junior licence holders during water stress. Cree Ative must disclose final water sources and volumes, including any licences or reallocations, and supply a noise assessment covering the combined effects of the plant and the data centre. Final design updates are due at least 90 days before construction of each applicable power plant phase.
The commission also required financial security for reclamation that would survive the operator's insolvency. One-third of the estimated cost is due at commercial operation of the first phase, two-thirds in year 15 and the full amount in year 20, with independent estimates refreshed every five years. The next public milestones to watch are the lease transfer, the final design and water filings, and ATCO's transmission application. The plant approval is now in hand. The grid connection the developer wants to use first is not.