November 27 is the last day to register to speak at a hearing that would change how the County of Grande Prairie handles data centre proposals. County council meets at 1 p.m. on Dec. 2 in Clairmont to consider a dedicated zoning district. That sounds like a matter of adding a label to a map. The consequential change is when residents learn what is proposed next door: an applicant would have to identify the land as a prospective data centre site before it could seek a development permit.

The draft amendment, Bylaw 2680-26-046, passed first reading on Oct. 5. If enacted, it would remove data processing establishments from the other zones where they are currently permitted or discretionary, including industrial districts. It would also strip data processing out of a combined printing and reproduction use definition. Its own definition expressly covers facilities that process data for artificial intelligence or digital currencies.

The county says its 2003 bylaw was written when data processing was often a smaller operation inside an office or commercial building. Today's projects can bring their own generators, cooling equipment and connections to regional utilities. An industrial designation might tell a neighbour to expect activity of some kind. It tells them little about which equipment might run overnight, or whether the proposed use would take up one building or a group of them.

What the new district would require

The proposed Data Centre Campus district, abbreviated DAT, has no automatically permitted uses. It lists data processing, electricity production and research facilities as discretionary uses for the Municipal Planning Commission. Offices, utilities and several related uses are discretionary as well. There would be a council decision on changing the zoning of a parcel, with a public hearing, followed by a separate decision on a development permit. Creating the new district on Dec. 2, if council completes the required readings, would not itself put any parcel in it.

Schedule A sets minimum lot sizes of 4,000 square metres for serviced land and 10,000 square metres for unserviced land. Its minimum side yard is eight metres on a serviced lot and 15 metres on an unserviced lot. It would leave maximum height to the development authority, which could also allow multiple buildings on a campus and require features such as berms or fences for screening or noise reduction.

Those yard figures describe the minimum distance between a building and a lot line under the draft. They are not stated distances from the nearest home or sound limits at a neighbour’s property. Nor does Schedule A specify how much water a facility could draw. That distinction gives council a concrete question to answer: what evidence should be in the public file before a parcel is rezoned, and which details can wait until there is a development permit application?

For a proposal with a cooling system and standby generators, for instance, a preliminary site plan could show how close equipment might sit to a home. A later engineering study could estimate what the equipment would sound like at that distance. Both have a purpose. But the timing matters to anyone trying to decide whether the proposed use belongs on that parcel in the first place. Water licensing and power approvals, where required, remain separate from the municipal process.

Three decisions, three separate files

The difference is visible in the county's record at Emerson Trail. On Sept. 4 it issued development permit PLDEV20250629 for a data processing establishment at 732041 Range Road 62, north of Highway 672. The permit included five buildings, 15 generators and 15 air or cooling units, according to the county. The land was already zoned for industrial development, and the county says it did not circulate the application to adjacent landowners before approving it because data processing was a permitted use. It posted the decision after approval.

That permit was appealed to Alberta’s Land and Property Rights Tribunal. The county still describes the appeal as being processed and says council cannot overturn the permit itself. The Dec. 2 hearing is about future rules, not a venue for council to decide that appeal. Nor does the September permit settle how much electricity or water the facility might use, which the county says depends on final design and separate processes.

Another Emerson Trail file goes to the Municipal Planning Commission on Dec. 8. That is a change-of-use application tied to PLDEV20260127, which the county approved in May for five buildings without specifying what they would be used for. The buildings have not been constructed. The new application would allow data processing in those buildings; the county says nearby residents were notified. It is a different file from the appealed September permit and a different decision from council's hearing six days earlier.

Public comments posted on the county’s engagement page include calls to disclose more about water use and potential effects on agricultural land before rezoning. Those submissions are the views of people who chose to comment, not a survey of the county. The hearing also leaves room for people who favour new investment, but want clear requirements at the outset so applicants and landowners can see what the county expects.

How to take part

The formal hearing takes place in council chambers at the County Administration Building, 10001 84 Avenue, Clairmont. The county's notice says people must register by Nov. 27 to speak, either in person or remotely. Its engagement page links the remote participation form and gives Legislative Services’ contact details. People who miss the speaking deadline can still send written submissions before the hearing starts, the notice says. Late submissions received before the start are shared during the meeting and added to the agenda package afterwards. Submissions may become public.

Read the hearing record for the date and text of any vote. The draft says it would take effect on third reading. The next test, if it passes, will be the first parcel up for rezoning under the new rules: how soon can people see the site plan, and what can council still change once they do?

Reporting sources